Skip to main content

The South Veterans Parkway project is a partnership with the South Dakota Department of Transportation (SDDOT) and the City of Sioux Falls.

Construction Updates

Through the winter, work on the bridge over the railroad tracks will continue, and all other construction is paused until spring.

Read Full Construction Details

What is the Speed Limit on Veterans Parkway?

As Veterans Parkway construction progresses, the City of Sioux Falls and South Dakota Department of Transportation (SDDOT) have planned roadway improvements to increase safety and promote consistency throughout the corridor. One of those includes changing the speed limit throughout Veterans Parkway to be 50 miles per hour. Crews have installed speed limit signs in completed sections, and new sections will have the same speed limit of 50 mph.

What is the construction schedule for South Veterans Parkway?

The first segment from Western Avenue to Cliff Avenue was completed in November 2024 and opened to traffic. Construction on the next segment from Cliff Avenue to Sycamore Avenue will begin in spring 2025. The remaining segments will continue to be designed and constructed through 2027.

How can I stay informed?

Updates on potential impacts will be shared via social media, email, and this website, when available.

Comments and questions can be emailed or submitted through our comment form.

View all FAQs

Click or tap on the icons to learn more about each segment of the new South Veterans Parkway.

I-29 to Western Avenue

Design: Complete

Construction: 2027-2028

Learn more

Western Avenue to Cliff Avenue

Design: Complete

Construction: Complete

Learn more

Cliff Avenue to Sycamore Avenue

Design: Complete

Construction: 2025-2026

Learn more

Sycamore Avenue to 57th Street

Design: Complete

Construction: 2027-2029

Learn more

Western Avenue to Cliff Avenue

Design: Complete

Construction: Complete

Learn more

What to Expect During Construction

  • Daily construction work
  • Construction materials and equipment
  • Trucks hauling materials
  • Noise during construction work hours
  • Dust management

About the Project

When connected to the northern segment of Veterans Parkway, the additional nine miles of roadway for South Veterans Parkway will support a regional arterial road network around southeast Sioux Falls. This project — the final stage in connecting Interstate 29 with Interstate 90 — will accommodate growing transportation needs across the corridor and help prepare the greater Sioux Falls area for continued vibrant growth and development.

The first segment from Western Avenue to Cliff Avenue was completed and opened to traffic in November 2024. Construction on the next segment from Cliff Avenue to Sycamore Avenue will begin in spring 2025. The remaining segments will continue to be designed and constructed through 2027. Learn more about each segment.

A timeline showing that construction begins in April 2025 and construction activities in spring, summer and fall of 2025 will include dirt work, storm sewer, and utilities on South Veterans Parkway and Southeastern Avenue, as well as paving on Southeastern Avenue. The timeline also shows that construction activities in spring, summer, and fall of 2026 will include dirt work and utilities on Sycamore Avenue and paving on South Veterans Parkway and Sycamore Avenue. The construction activities are weather and schedule permitting.

Project Benefits

  • Increased traffic flow
  • Corridor connectivity
  • Accommodate public and private investment