Skip to main content

speedometer iconUPDATE: The speed limit throughout Veterans Parkway will be 50 miles per hour.

Western Avenue Settlement: We are aware of the settlement issue on Western Avenue between County Road 106 and Veterans Parkway. We have been monitoring the settlement and are in the process of evaluating options to fix the issue. We will continue to update the website with additional information as we determine a fix. Signage has been placed warning drivers to slow down.

The South Veterans Parkway project is a partnership with the South Dakota Department of Transportation (SDDOT) and the City of Sioux Falls.

Thursday, July 31, 2025 Construction Updates

  • Southeastern Avenue and Sycamore Avenue are both closed to traffic near the future South Veterans Parkway intersections. The detour routes are Cliff Avenue and S.D. Highway 11.
  • Construction of the bridge over the railroad has begun. The contractor will be driving steel piles into the ground in August. Pile driving creates additional noise and may be noticeable if you are near the construction area.
  • While school is out for the season, the contractor is working to complete improvements at the intersection of Southeastern Avenue. Bison Trail improvements are complete.
  • Both pedestrian underpasses located between Cliff Avenue and Sycamore Avenue are complete.
  • Underground utilities are fully installed near Southeastern Avenue, and crews are continuing to haul material on the east side of the roadway.
  • Construction on Southeastern Avenue from 69th Street to 85th Street will continue through the summer and is currently anticipated to reopen in late fall, weather dependent.
  • The temporary railroad crossing within the construction area is still in place, allowing equipment and materials to be moved across the railroad tracks as work on the new road segment continues.
  • Dirt is being hauled from a borrow pit near Cliff Avenue to the area between the railroad tracks and Cliff Avenue to build up the road embankment.

Read Full Construction Details


Click or tap on the icons to learn more about each segment of the new South Veterans Parkway.

I-29 to Western Avenue

Design: 2023-2024

Construction: 2024-2025

Learn more

Western Avenue to Cliff Avenue

Design: Complete

Construction: Complete

Learn more

Cliff Avenue to Sycamore Avenue

Design: 2023-2024

Construction: 2025-2026

Learn more

Sycamore Avenue to 57th Street

Design: 2024-2025

Construction: 2026-2027

Learn more

Western Avenue to Cliff Avenue

Design: Complete

Construction: Complete

Learn more

What to Expect During Construction

  • Daily construction work
  • Construction materials and equipment
  • Trucks hauling materials
  • Noise during construction work hours
  • Dust management

About the Project

When connected to the northern segment of Veterans Parkway, the additional nine miles of roadway for South Veterans Parkway will support a regional arterial road network around southeast Sioux Falls. This project — the final stage in connecting Interstate 29 with Interstate 90 — will accommodate growing transportation needs across the corridor and help prepare the greater Sioux Falls area for continued vibrant growth and development.

 

The first segment from Western Avenue to Cliff Avenue was completed and opened to traffic in November 2024. Construction on the next segment from Cliff Avenue to Sycamore Avenue will begin in spring 2025. The remaining segments will continue to be designed and constructed through 2027. Learn more about each segment.

Project Timeline
  • April 2025 - Construction Begins
  • Spring to Fall 2025 - Dirt Work, Storm Sewer, and on South Veterans Parkway and Southeastern Avenue; Paving on Southeastern Avenue
  • Spring to Fall 2026 - Dirt Work and Utilities on Sycamore Avenue; Paving on South Veterans and Sycamore Avenue
  • Weather and Schedule Permitting

Project Benefits

  • Increased traffic flow
  • Corridor connectivity
  • Accommodate public and private investment

When is construction?

The first road segment from Western Avenue to Cliff Avenue was completed in November 2024. The segment from Western Avenue to Sycamore Avenue will be constructed next, with the remaining two segments still in design.

Learn More

How can I stay informed?

Updates on potential impacts will be shared via social media, email, and this website, when available.

Comments and questions can be emailed or submitted through our comment form.

How is the project being funded?

This project is funded in partnership by the South Dakota Department of Transportation (SDDOT), the City of Sioux Falls, the Sioux Falls Metropolitan Planning Organization (MPO) and the Federal Highway Administration (FHWA). The project will cost approximately $210 million.

View all FAQs

Quotes

We are grateful to the Governor's Office and the South Dakota Department of Transportation for making this critical investment in roadway infrastructure...

- Sioux Falls Mayor Paul TenHaken

As South Dakota's economy continues to grow, it's crucial that we finalize this major infrastructure investment in Sioux Falls. The Veterans Parkway will enhance economic opportunities for the city and the surrounding area...

- Governor Noem